ERP Implementation Failure: Vital Farms, Zimmer Biomet, Lamb Weston, and How to Avoid Being Next

One company cut its guidance after its ERP go-live and drew a shareholder lawsuit. Another is suing its integrator for $172 million. A third lost about $135 million of sales in one quarter. The failures share a shape: one big switchover, heavy customization, and no way to stop halfway. Here is where each case stands, and the alternative.

Oct 17, 2026

Updated

A huge tangled machine leaking cubes next to a stalled delivery truck, beside a steady core block with one clean glowing module attached and others waiting in line

ERP implementation failures rarely fail in the software. They fail at go-live, in shipments, invoices and inventory, and they keep failing in public. Vital Farms switched ERP on 29 September 2025, cut its revenue outlook in December, and drew a shareholder lawsuit in March 2026. Zimmer Biomet is suing Deloitte for at least $172 million over an SAP S/4HANA implementation it calls overly customized and defective. Lamb Weston said its 2024 ERP switch cut one quarter's net sales by about $135 million, and its shareholder suit is still alive. Different companies, same shape: one big switchover, heavy customization, and no way to stop halfway. Below: where each case stands in November 2026, why ERP projects fail, how to rescue one that is going wrong, and how to change your systems in slices you can stop.


ERP lawsuits: where each case stands (November 2026)

CaseWhat went wrongStatus
Vital Farms shareholder suit (Texas)Go-live 29 Sep 2025, outlook cut in Dec 2025 citing order disruptionLead plaintiff appointed July 2026; amended complaint filed; motion to dismiss due 24 Nov 2026
Zimmer Biomet v. Deloitte (New York)SAP S/4HANA go-live 4 July 2024; $172 million claimedMotion to dismiss filed Nov 2025; no reported ruling or settlement
Lamb Weston shareholder suit (Idaho)North American ERP switch in early 2024; about $135 million of sales lost in one quarterPartly survived a motion to dismiss in May 2026; second motion to dismiss pending

All three are allegations, not findings. None has been decided on the merits.

Vital Farms: a go-live, a guidance cut, a lawsuit

From Vital Farms' own filings with the SEC, and the securities complaint as reported by TipRanks:

  • May 2025: per the complaint, the CFO said the ERP launch had moved from summer to early fall "to ensure a flawless switchover".
  • 29 September 2025: go-live. On 4 November the company raised its 2025 revenue guidance to at least $775 million and said it had gone live "without disrupting service to our retail partners in any major way".
  • 16 December 2025: guidance cut to $755 to $765 million, reflecting "a temporary disruption in returning to regular order patterns" after the ERP transition. The company said it had left the ERP "hypercare" phase on 5 December.
  • 26 February 2026: 2025 net revenue came in at $759.4 million, inside the cut range and below the November figure. Plaintiffs' firms say the stock fell 10.8% that day.
  • 27 March 2026: shareholders sued in federal court in Austin, alleging the ERP risks were described as hypothetical when they were already happening.
  • Since then: per the company's Q3 2026 quarterly report, the court appointed Xiaohu Wang as lead plaintiff in July 2026, an amended complaint was filed on 25 September 2026, and the defendants' motion to dismiss is due 24 November 2026. A related shareholder derivative suit is stayed until the class action is resolved. The company says it will defend itself.

Zimmer Biomet v. Deloitte: $172 million, no ruling yet

From the complaint as reported by Loeb & Loeb and Becker's. Again, allegations:

  • Filed on 4 September 2025 in New York Supreme Court, seeking at least $172 million.
  • Zimmer Biomet says Deloitte assured it could deliver SAP S/4HANA on time and on budget with minimal customization, then delivered an overly customized system with defects after $94 million in fees.
  • The system went live in North America on 4 July 2024, after repeated delays, and Zimmer Biomet claims tens of millions in remediation and disruption to operations and the supply chain.
  • Deloitte calls the claim meritless. It moved to dismiss on 7 November 2025, arguing among other things that Zimmer Biomet did not give the breach notice the contract required. Zimmer Biomet opposed in December 2025.
  • Has it been settled? Who won? Neither, as far as public reporting shows. We found no ruling on the motion and no settlement as of November 2026.

Lamb Weston: $135 million of sales in one quarter

Lamb Weston, the frozen potato maker, moved order to cash, inventory and purchasing in North America to a new ERP at the start of its fiscal third quarter of 2024. In its April 2024 results it said the switch "temporarily reduced the visibility of finished goods inventories" at its distribution centers, cut net sales by about $135 million and net income by about $72 million in the quarter, and lowered its full-year guidance.

Shareholders sued in Idaho in June 2024. Per the company's latest quarterly report, on 12 May 2026 the court dismissed part of the case, including some ERP-related statements, but let the rest go on. A second motion to dismiss was fully briefed in October 2026.

Other famous ERP failures

  • Revlon (SAP, 2018): service disruptions at its Oxford, North Carolina plant after go-live. A 2019 investor suit cited about $64 million of net sales in unfulfilled shipments, per TechTarget.
  • Lidl (SAP, 2011 to 2018): a seven-year project to replace its in-house inventory system, abandoned with losses Panorama Consulting puts at about $580 million.
  • Hershey (1999): about $100 million of orders it could not fill after go-live, per the same Panorama list.
  • Birmingham City Council (Oracle, UK): budgeted at £19 million, now forecast at £144.4 million and still being reimplemented, per The Register in January 2026.

What percentage of ERP implementations fail?

Nobody knows precisely. The "55% to 75% of ERP projects fail" line is everywhere, and we could not trace it to a published study, so we don't repeat it. The most useful survey we found is narrower: Panorama Consulting polled 131 organizations between August 2022 and December 2023, and 32.8% finished over budget, 31.3% finished late, and 2.3% got no benefit at all.

So most ERP projects don't collapse. About a third run over. The ones that become lawsuits are the ones where go-live breaks shipping, billing or inventory, because that is when customers and investors notice.

Why ERP projects fail

The same causes show up in almost every case:

  1. The big bang. Every process switches on one date. If anything is wrong, everything is wrong, and there is no road back.
  2. Customizing the core. A standard product is bent to match every existing habit, and each customization becomes something to test, maintain and break on the next upgrade.
  3. Data migration underestimated. Years of inconsistent customer, item and price data meet a system that expects it clean.
  4. Testing with demo data. The system works on fifty clean orders and fails on a real Monday morning.
  5. A date set by the calendar, not by readiness. "Early fall" becomes a commitment to investors before anyone knows whether it is achievable.

Small companies fail the same way, just without the lawsuit. A common sign: after the migration, reporting is broken. The reports were built on the old data model, nobody mapped them, and month-end now runs on exports and spreadsheets.

How to rescue a failing ERP implementation

If you are already live and it hurts:

  1. Stop adding scope. No new modules, no new customizations, until orders ship and invoices go out.
  2. Find the one broken process. It is usually order to cash, inventory visibility, or billing. Measure it with real orders, not tickets.
  3. Check the data, not just the code. Compare migrated customers, items and prices against live records. Many "bugs" are bad data.
  4. Decide per process: fix the configuration, build a small tool next to the ERP to get through, or roll that one process back.
  5. Get an outside read of the custom code, integrations and migration scripts before you sign the next change order.

We don't configure SAP or Oracle. What we do is the part around them: read the custom code and integrations, and build the module or connection that gets one process working again.

The alternative: change in slices you can stop

Keep what works. Most companies don't need to replace their whole ERP. The ledger works, inventory mostly works, and what hurts is one process: quoting, a customer portal, shipping, planning, a field workflow. That process can be built as a separate module next to the ERP, connected through its API, without touching its core.

One process at a time. Each slice moves one process, with its own data migration and its own testing on real records, and goes to production before the next one starts.

A stop point after each slice. Every slice ends with something in production and a decision: continue, change course, or stop, with what you built still working.

Keep customization out of the core. If the ERP can't do it as standard, build it next to it, where it can be tested and changed without risking every upgrade.

We have done this kind of work for clients:

What it costs instead of a big bang

Our published prices, in US dollars:

PriceWhat you get
Starter$1,900 fixedOne small tool or one connection next to your ERP, on your own data in about two weeks, credited against the first slice
Code audit$2,900 fixedFor a stalled project: what is sound in the custom code and integrations, what is not, and a costed plan
First slice$5,000 to $18,000One process in production, connected to your ERP
Complete module$18,000 to $45,000Several processes with integrations, delivered slice by slice
Running itFrom about $470 a monthHosting, monitoring, updates; you own the code

You can stop after any slice, and what you built keeps working.